Hassan II Stadium in Fez is getting a new lease on life. After hosting matches for Maghreb de Fès (MAS) and Wydad Athletic de Fès (WAF) for several decades, the historic venue is undergoing a complete reconstruction that will increase its capacity to 15,000 spectators.
During a visit to the construction site, Le360 saw the scale of the work underway. Concrete structures, stands and interior spaces are taking shape, with construction teams working on several fronts to give the historic facility a new look.
Mehdi Rahmaoui, project director at TGCC, the company in charge of the work, told Le360 that the structural work was 85% complete. This stage is expected to be finished by the end of November 2026, before technical work continues and the various facilities and equipment are installed.
Reconstruction began last March with the complete demolition of the old stadium. Earthworks and site preparation got underway in mid-June, followed by the construction of underground levels, concrete structures and the supporting elements of the stands.
Le chantier de reconstruction du Grand Stade de Fès.
Work is now focused on electrical installations, power systems and ventilation equipment. Construction of the stands is also continuing, while teams are preparing to lay the pitch.
15,000 seats in two phases
The new stadium will have a total capacity of 15,000 spectators, up from 10,000 previously. Its design allows for all the stands to be covered, but the first phase of construction provides for roofing only the official stand, located on the western side of the stadium.
The second phase will complete the stadium’s exterior roofing. Facilities for the general public, as well as dedicated areas for dignitaries and special guests (VIP and VVIP), are also planned.
The first phase is expected to be completed by the end of March 2027. It will include the completion of the structural work, architectural finishing and roofing of the western section, where the official stand will be located. However, this deadline does not mark the final delivery of the stadium.
To meet the schedule, between 650 and 700 workers from various trades are currently involved in the project. Teams are working around the clock, with constant coordination between the different trades to speed up construction.
The total cost of rebuilding Hassan II Stadium is estimated at around 400 million dirhams. Documents accompanying the 2027 Finance Bill also include an allocation of 20 million dirhams for the facility, pending funding for the remaining stages of the project.
Read also : Fez’s Hassan II Stadium: Main structural works expected to finish by end of November
Beyond its sporting purpose and its historic role as the home ground of MAS and WAF, Hassan II Stadium is also expected to form part of the facilities supporting the 2030 FIFA World Cup, serving as a training venue for participating national teams.
The reconstruction is part of the broader effort to modernize Morocco’s sports infrastructure ahead of the global tournament. Fez is thus continuing to upgrade its facilities as the country prepares for 2030.