Speaking to Morocco’s news agency MAP on Thursday during a media visit to the construction site, Rahmaoui said the main structural works should be wrapped up by the end of this month. The first phase also includes technical installations and the roofing of the stadium’s western section, with all work expected to be completed by the end of March.
The schedule reflects progress across the various parts of the project, which began in June after the demolition of the old stadium and the completion of excavation and site preparation work.
Read also : Morocco’s 2030 stadium map takes shape: Two ready, three under overhaul, one giant rising
Between 650 and 700 workers are currently employed at the site, across several trades and specializations. This allows different construction operations to move forward simultaneously while requiring close coordination between the teams.
The new stadium will have a capacity of 15,000 spectators. Work is continuing on its various structures, as well as on facilities being developed on the underground levels.
Rahmaoui said carrying out these operations in parallel requires ongoing coordination between the teams and the different trades involved in the project.
A second phase is also planned, focusing in particular on completing the stadium’s exterior cladding.
The site visit gave local and national media representatives an opportunity to see the progress firsthand, observe the ongoing work and learn about the next stages of construction.