Casablanca’s Larbi Ben Barek and Tessema stadium projects advance ahead of 2030 World Cup

Larbi Ben Barek Stadium in Casablanca undergoing renovation

Work is progressing on the renovation of the historic Larbi Ben Barek Stadium and the construction of a new 30,000-seat venue at Tessema, with completion scheduled for 2027 and 2028, respectively.

On 25/11/2026 at 20h30

Two major stadium projects are taking shape in Casablanca as part of Morocco’s preparations for the 2030 World Cup. While Larbi Ben Barek Stadium is undergoing extensive renovation, the former Tessema ground has been demolished to make way for a new venue with a capacity of 30,000 spectators.

Larbi Ben Barek Stadium undergoes major renovation

Located in the Sidi Belyout district, Larbi Ben Barek Stadium, formerly known as Philip Stadium, is one of Casablanca’s oldest sporting venues. It was added to the city’s architectural heritage list last October.

Renovation work is currently focused on the stands and their roofing. Metal structures have been installed along the terraces, while the old playing surface has been completely removed. Construction equipment and building materials now occupy part of the pitch.

Work began last April, making it the first stadium in Casablanca’s football infrastructure upgrade program to enter the renovation phase. The project involves a major overhaul while preserving part of the venue’s original architectural structure.

One of the main priorities is to redesign the stands. Their previous layout posed a risk of spectators falling from the upper sections.

The renovation plan also includes installing individual seats, replacing the entire playing surface, upgrading the changing rooms and fitting a new LED lighting system that meets FIFA standards.

The project is part of a wider sports infrastructure modernization program led by the Ministry of National Education, Preschool and Sports and the Royal Moroccan Football Federation (FRMF), in partnership with SONARGES, the National Agency for Public Facilities (ANEP) and Casa Aménagement.

The renovation is expected to be completed in 2027. The stadium is then set to serve as a training ground for national teams competing at the 2030 World Cup before returning to its role as a venue for youth development and local competitions.

Tessema to become a 30,000-seat stadium

Unlike Larbi Ben Barek, which is being renovated, Tessema Stadium in the Sidi Othmane district has been completely demolished to make way for a new 30,000-seat venue.

Demolition and excavation work have been completed. Several cranes and construction vehicles are now operating on the site, where structural work is underway.

Following the initial work entrusted to SNTRO, the main reconstruction contract was awarded to TGCC Group last August, with an 18-month completion period.

The new stadium will cover 6.62 hectares and feature 30,000 seats, all under cover. The architectural plans also include dedicated media and VIP areas, a facade with dynamic lighting and facilities designed to meet international standards.

The project is being led by the FRMF, with ANEP serving as the delegated project owner. Work is also progressing on the stadium’s technical installations.

The new venue is expected to be delivered in the first half of 2028. It will host training sessions for national teams taking part in the 2030 World Cup, as well as matches involving Casablanca’s clubs.

By Omar Nabile