Published in Spain’s Official State Gazette on November 12, 2026, the document includes Morocco among the interconnections considered in the country’s 2025-2030 electricity network plan.
The strategic environmental assessment, dated November 3, marks another administrative step in Spain’s grid planning. It does not amount to final approval to build the third submarine cable, nor does it signal the start of construction. The project, first announced in 2019, has already seen its original timetable revised and its projected cost reassessed.
The main questions raised by Spanish regulatory documents concern how the infrastructure will be financed, whether its economic benefits justify the investment and how technical challenges could affect construction.
Costs nearly double despite reduced technical specifications
In a report dated June 9, 2026, Spain’s National Commission on Markets and Competition (CNMC) noted that the projected investment for the third interconnection had increased from €234.7 million under the 2021-2026 planning period to €434.6 million in the proposal for 2025-2030. That represents a rise of around 85%.
The increase is all the more striking because some of the project’s technical specifications have been scaled back, the regulator noted. The number of planned electrical bays has been reduced from six to four, while the proposed length of the submarine cable has fallen from 52 to 42 kilometers.
Read also : African Atlantic Gas Pipeline: A decade later, Morocco’s vision has West Africa on board
The CNMC said the planning proposal did not sufficiently explain these changes, particularly given the higher unit costs.
Financing arrangements between the two countries are another issue under scrutiny. The regulator has asked for clarification on the investments attributable to the Spanish side, particularly if Morocco and Spain have reached an agreement to share the costs.
It has also called for a more detailed assessment of the project’s expected economic benefits. Since Morocco is not a member of the European Union, the CNMC says the proposal must demonstrate that the benefits for Spanish consumers will justify the investment borne by Spain’s electricity system.
The project dates back to February 14, 2019, when Morocco and Spain signed a memorandum of understanding during the Spanish royal couple’s visit to the Kingdom. The agreement tasked Morocco’s National Office of Electricity and Drinking Water (ONEE) and Spanish grid operator Red Eléctrica with carrying out the technical and economic studies needed for the project.
Commissioning now envisaged around 2030
The third link is designed to have a technical capacity of 700 megawatts (MW). It would complement the two existing interconnections between the countries, which entered service in 1997 and 2006 and have a combined technical capacity of 1,400 MW. The new cable would bring total capacity to 2,100 MW.
When the project was announced in 2019, its estimated cost stood at around €150 million, including €75 million for the Spanish section. It was then expected to enter service before 2026. That initial estimate cannot be directly compared with figures in later planning documents without accounting for changes in the project’s scope and calculation methods.
Seven years later, the Spanish planning proposal now points to 2030 as the target horizon for commissioning. That date remains dependent on several technical and financial factors.
The CNMC report also highlights the engineering challenges involved in crossing the Strait of Gibraltar. The depth of the seabed, strong currents and uneven underwater terrain require specific solutions for laying and protecting the cables.
There are also pressures on the submarine equipment market, including limited availability among specialized suppliers and the risk of further cost increases.
The regulator warns that these difficulties could push commissioning back to 2033 or 2034. This is not an officially adopted new timetable but a risk scenario that the CNMC says should be taken into account in technical and financial assessments.
The documents therefore identify several obstacles to completing the infrastructure, without establishing precisely why the original schedule has changed.
A strategic link for Morocco’s electricity supply
Beyond the technical and financial questions, the third interconnection is important for Morocco’s electricity supply security and the development of energy exchanges with Spain.
The two existing links already allow electricity to flow in both directions across the Strait of Gibraltar. Recent figures, however, show that Morocco remains a major net importer of electricity from its northern neighbor.
Provisional figures from Red Eléctrica for 2025 show that scheduled electricity exchanges between the two countries resulted in a net balance of 3,743 gigawatt-hours (GWh) in favor of Spanish exports, up from 2,537 GWh in 2024. This was the highest level recorded since 2017.
The figures show that electricity exchanges remain heavily tilted toward Moroccan imports from Spain. The existing infrastructure nevertheless also allows Morocco to export electricity to its neighbor.
Read also : Automotive industry: ‘Made in Europe’ opens a new strategic chapter in Morocco-EU talks
Expanding the integration of renewable energy
The importance of these links was demonstrated during the major power outage that hit the Iberian Peninsula on April 28, 2025. Morocco helped restore Spain’s electricity supply through the existing interconnections, as part of coordinated operations between the two countries’ grid operators.
In this context, a third link would increase the technical capacity for electricity exchanges and create more opportunities to integrate renewable energy. It could also give grid operators greater flexibility in managing electricity networks, provided the necessary investments are made.
The key question is when the infrastructure will actually be built. Although the Spanish planning proposal points to 2030, the regulator’s concerns over costs and technical challenges leave the project’s timetable uncertain.